The project name is very well defined in itself. Rohini River forms its Western boundary, Nagar Nigam limits its Northern boundary, NER Track to Nautanwa lies in its East whereas NER Track to Lucknow forms its Southern Boundary. This Zone includes wards 8, 16, 22, 32 (Partially), 44(Partially), 29(Partially), 70(Partially), 23, 43(Partially), 12, 40(Partially), 11, 48, 41(Partially), 69(Partially), 10, 61(Partially), 64(Partially), 49(Partially), 50, 33, 58(Partially), 68 and 56. The Design Population and Anticipated sewage contribution for various Design Stages have been tabulated below.
Construction of sewer line for a total length of about 57.08 km, with its appurtenant works, H.C.C., S.C.C, H.C.
Constructing STP of 10 MLD on SBR Technology on a module basis, such as on the available site area of about 4 acres, the proposed 10 MLD STP (pre-treatment units for 40 MLD witha peak factor of 2.25) is to be extended up to 40 MLD capacity.
MPS with Civil structure for 40 MLD average flow (with peak factor 2.25) and E&M works for 22.5 MLD peak flow, including 100% standby pumping capacity.
Constructing civil work of the Treated euent pumping station for an average discharge of 40 MLD, for which E&M works will be for 10 MLD average discharge.